Federal Executive Council (FEC) Approved Contracts for June 17, 2009

Posted by Chinyere on Fri 05th Oct, 2012 - nigeriantenders.com






FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS FOR JUNE 17, 2009

1) Award of Dams and Irrigation Projects and Contracts for the Construction of New Dams and Irrigation Projects Nationwide as Follows:

 

Projects: Completion of Sabke Irrigation project in Katsina State

Main Line Budget(A): 1,199,170,167.94

Special Intervention Fund(B): 1,068,000,000.00

Total: 2,267,170,167.94

Contractor: Messrs. Doliz Brown (Nig) Ltd.

Duration: 24 Months

 

Projects: Ogbese Dam Project in Ekiti State

Main Line Budget(A): 5,493,689,557.13

Special Intervention Fund(B): 0.00

Total: 5,493,689,557.13

Contractor: Messrs. Foundation Solid(Nig.) Ltd.

Duration: 24 Months

 

Projects: Zobe Irrigation Project in Katsina State

Main Line Budget(A):  6,869,686,518.17

Special Intervention Fund(B): 0.00

Total: 6,869,686,518.17

Contractor: Messrs. CGC (Nig.) Ltd.

Duration: 24 Months

 

Projects: New Nigerian Farmers Irrigation Projects in Kwara State

Main Line Budget(A):  2,802,818,716.90

Special Intervention Fund(B): 0.00

Total: 2,802,818,716.90

Contractor:  Messrs. CGC (Nig.) Ltd.

Duration: 24 Months

 

Projects: Procuring and installing Centre Pivot Irrigation System Spread in Various Locations

Main Line Budget(A): 3,714,648,556.00

Special Intervention Fund(B): 2,000,000,000.00

Total: 5,714,648,556.00

Contractor:  i). Messrs. Reinke Manufacturing ii). Messrs. Millennium Benefit LLC

Duration: 4 Months

Total Cost

Main Line Budget(A): 20,231,620,664.14

Special Intervention Fund(B): 3,068,000,000

Total: 23,299,620,664.14

 

2) Item/Service: Award of the Contract for the Construction of an Inland River Port at Oguta Lake, Imo State

Name of Company: Messrs. Scott Amede Engineering Limited

Cost: N 2,743,625,787.15

Date: 17/06/09

Duration: 24 Months

 

3) Item/Service:  Award of Contract for the Supply of 25No. New C25- EMPD Diesel Locomotives

Name of Company:  Messrs. General Electric (GE) Transportation Gevisa, S.A.

Cost:  USD 76,250,000.00 Exclusive of Freight handling, port fees, custom duty and taxes.

Date:  17/06/09

Duration: 8 Months

 

4) Item/Service:  Approve the Revision of the Contract Sum for the Construction of Umuahia 2x30/40MVA, 132/33KV Substation and 2x132KV* Line Bay Extension at Alaoji 132 KV Switchboard

Name of Company:  Messrs. Valenz Holding Limited

Cost:  Revised contract sum from USD6,751,845.79 Plus N204,915,480.00 to USD7,063,399.48 Plus N500,300,649.00

Date:  17/06/09

Duration: 6 Months

 

5) Item/Service: Ratify the anticipatory approval for the revision of Contract sum for Gombe- Yola-Jalingo 330KV SC Transmission Line Project

Name of Company:  Messrs. Chrome Construction Energy Ltd.

Cost:  Revised contract sum from USD 63,250,000.00 to USD 76,762,626.44

Date:  17/06/09

Duration: 6 Months

 

6) Item/Service: Award of the Contract for the Design, Manufacture and Supply of 16No. 330KV Instrument Transformers

Name of Company:   Messrs. Siemens (Nig.) Ltd.

Cost:   Euro 1,928,490.00 Plus N61,197,694.99

Date:  17/06/09

Duration: 4 Months

 

7a) Award of Contracts for the Construction of two Additional Silo Complexes

Date:  17/06/09

Duration: 12 Months


7b) Serial No.:
1

Location: Uyo, Akwa Ibom State

Name of Company: Messrs. Trenur(Nigeria) Limited

Contract Sum (N): 1,737,452,981.02

Silo Capacity: 25,000MT

 

7b) Serial No.: 2

Location: Abuja, FCT

Name of Company: Messrs. Metropole Development Co. Ltd.

Contract Sum (N): 4,174,766,757.52

Silo Capacity: 100,000MT

Grand Total:  N5,912,219,738.54

 

8) Item/Service: Award of Contract for the Provision of 2,600 Units of Tractors and Implements for the Implementation of the Tractor Hiring Scheme under the Public Private Partnership (FGN 25% Contribution Grant)

Name of Company:    

i).Messrs. Labana Global Ventures Limited (Type-HP 75 Qty- 600 Units)

ii).Messrs. TAK Tractors(Nig.) Ltd( Type-HP 75 Qty- 1000Units)

iii).Messrs. Agric Supermarket Ltd. ( Type- HP 75 Qty- 1000Units)

Cost: N4,739,250,000.00

Date:  17/06/09

Duration: 90 Days

 

9) Item/Service: Award of Contract for Resident Supervision of the Roads and Bridges as well as Water, Storm Water Darinage, Foul Sewage, Electricity and Telecommunication aspects of the Construction of Roads B6, B12, Circle and other Arterial Roads in the Central Area of the Federal Capital City, Abuja

Name of Company: Messrs. Yolas Consultants

Cost: N331,986,696.83   

Date:  17/06/09

Duration: 48 Months

 

10) Item/Service: Approve the Variation of the Contract for the Completion of the Shehu Shagari Presidential Complex

Name of Company:  Messrs. Gitto Construzioni Generali (Nigeria) Limited

Cost: Revised contract sum from N2,650,000,000.00 to N3,228,575,454.79

Date:  17/06/09

Duration: 24 weeks